Project Construction Timeline

Below is an outline of the key dates of the Goose  Harbour Lake Wind Farm project's construction. This timeline generally represents certain key milestones that can be expected in the coming years. Note, this is subject to change.

2024

4th Quarter

  • Limited Civil construction
    begins

2025

1st Quarter

  • Batch Plant and laydown area cleared
    ‍‍
  • Turbine site grubbing starts

2025

2nd Quarter

  • Site and logistic route roads, water crossings, turbine site excavation
    ‍‍
  • Pouring mud mats
  • Site Trailers set up
  • O&M & substation construction kickoff

2025

3rd - 4th Quarter

  • Turbine site work, roads, water crossings
  • Transmission line, switching station and collection system construction begins
  • Batch plant operational
  • Turbine foundation pouring

2026

1st - 3rd Quarter

  • Any remaining turbine foundations completed
    ‍‍‍‍
  • T-line, switching station, substation and collection system completion
    ‍‍
  • Wind turbine delivery and erection

2026

4th Quarter

  • Completion of wind turbine erection and commissioning
    ‍‍‍
  • Commercial Operation Commences
    ‍‍‍