Below is an outline of the key dates of the Goose Harbour Lake Wind Farm project's construction. This timeline generally represents certain key milestones that can be expected in the coming years. Note, this is subject to change.
2024
4th Quarter
Limited Civil construction begins
2025
1st Quarter
Batch Plant and laydown area cleared
Turbine site grubbing starts
2025
2nd Quarter
Site and logistic route roads, water crossings, turbine site excavation
Pouring mud mats
Site Trailers set up
O&M & substation construction kickoff
2025
3rd - 4th Quarter
Turbine site work, roads, water crossings
Transmission line, switching station and collection system construction begins
Batch plant operational
Turbine foundation pouring
2026
1st - 3rd Quarter
Any remaining turbine foundations completed
T-line, switching station, substation and collection system completion
Wind turbine delivery and erection
2026
4th Quarter
Completion of wind turbine erection and commissioning