Construction has ramped up this month at PHPWind’s Goose Harbour Lake Wind Farm. We recently surpassed 100 workers on site, with the majority of the current construction effort focused on road and wind turbine pad construction. New culverts have been delivered to the site and are being installed according to the terms of our environmental permits.
Construction trailers and temporary power are now in place at the project laydown area at 127 Hayden Road, near the intersection with Old Mulgrave Road.
Civil work at the project substation has commenced, and we anticipate starting substation foundation work soon.
Ordering of engineering equipment and materials continues. Rebar, anchor bolts, and specialized formwork for the wind turbine foundations are being delivered. We expect construction of wind turbine foundations to begin by August 2025.
Wind turbine blades are scheduled for fabrication in the coming month. We remain on schedule with turbine component manufacturing and delivery, with the wind turbine package delivery to the Port of Mulgrave expected to start by April 2026. The project remains on schedule as per our website (www.phpwind.ca)
If you have any questions, please email info@phpwind.ca, visit the contact page on our website, or contact one of your Community Liaison Committee members.